This was the most sloppily managed aspect of the Workcamp. I cannot use my being a first-timer as an excuse. I could have organized a risk identification workshop with the people with Workcamp experience. But I didn't. So to make up for it, here's a post-project Risk Breakdown Structure for the Workcamp. I'm embarrassed to say this, but during the planning, I only identified two (2) risks, a storm and not having sufficient work for the volunteers (I'm an optimist). This RBS has more than 60 risks. It will be useful for the next Workcamp.
What I'll do next time- Reuse this RBS
- Have a risk identification workshop with my core team
- Come up with a risk register with options for mitigation and contingency. See an example of a Risk Register.
DocumentsBack to the table of contents
2 comments:
safety course in chennai
construction safety courses in chennai
Industrial safety courses in chennai
fire and safety courses in chennai
Iosh course in chennai
Yay! Thank for taking time to share these lessons. They will really helped us a lot. Mindman Distributor Philippines
Post a Comment